Corus Rod Mill installation
When a sudden requirement for a skilled installation arose, we were able to provide that team and work to very exacting standards.
We were involved with the mechanical installation of roughing stands (around 100metres in total) for the new rod mill furnace and we had a surveyor on site ensuring alignment of the equipment to very high tolerances.
Production Plant Build
We worked closely with FLSmidth on this project - FLSmidth supplied all the mechanical equipment and we carried out all the installation work for Plasmor.
This project required a pair of kilns with a total length of around 50m, weighing around 100 tons to be supplied and installed. Although access on the site was good, moving the 100 ton sections to the installation point created its own problems. A new road had to be built on site to get the kilns to their final destination.